Coming into the month of October, several CIP projects continue to progress forward. Here are some of the highlights, including some behind-the-scenes updates, that are happening at the Center of Hospitality:
The West Building Wall Panels are receiving a makeover. Replacement of the wall panels and a fresh coat of paint gives the interior of the West Concourse a facelift to match the modern décor of the building. The expected completion date for this update is February 2018.
West Building Hall C Pavement Repair is in the final stages of clean up. It is open for roadway traffic and operations are back to normal.
Valencia Ballroom Dressing Room A, the final dressing room to be remodeled, has reached completion. The updated space has been equipped with all-new LED vanity lighting, an updated bathroom facility and modern décor. It is expected to be fully open for business by the end of October 2017.
The Chapin Theater Dressing Rooms & Green Rooms are in general construction and making progress toward an expected completion date of October 2017.